How is the WIP KPI calculated

Postby MelBond » Wed Dec 14, 2016 10:33 am

Good morning,

Can you please provide information on what elements of UniPhi are used to calculate the WIP KPI, and what determines a high alert?

many thanks

mheath73
Posts: 25
Joined: Fri Jun 20, 2014 2:18 pm

Re: How is the WIP KPI calculated

Postby mheath73 » Fri Jan 06, 2017 2:24 pm

Hi Mel,

WIP is based off the earned value of the project. Earned value % is calculated by dividing actual costs by total forecasts cost. Earned value $ is calculated by multiplying this % by the total forecast revenue for the project. WIP is then the difference between this number and the invoiced value for the project.

This calculation is explained in our financial management manual (pages 13 and 14). This can be downloaded from our community page of the website

http://uniphi-software.com/community/

All these values can be seen in the Project Analysis report in the profitability tab. The indicator colours are proprietary so that project managers need to spend time if they wish to game the system.